You will find all the delivered products as documents.
The deliverable products accordingly to application part C.
Project Web Site delivered 14/10/2011 (original deadline 01/10/2011)
Notice Boards first delivery 14/10/2011 (original deadline 01/11/2011)
A plan for the implementation phase 01/12/2011
Monitoring protocol delivered 27/03/2012 (original deadline 01/12/2011)
Initial report delivered 21/03/2012 (original deadline 30/11/2011)
LCA of PVC blood bag delivered 23/03/2012 (additional deliverable)
Presentation of the LCA delivered 08/02/2012 (additional deliverable)
Inception Report delivered 30/03/2012 (original deadline 01/04/2012)
Progress report not req by EC ready 30/09/2012 (original deadline 01/08/2012)
Progress report 1 delivered 01/02/2013
MidTerm Report delivered 30/09/2014 (original deadline 30/10/2013)
Progress Report 2 delivered 28/02/2016
Audit Result (new deadline 10/09/2017)
Economic feasibility study 30/06/2017
Final Layman’s report (new deadline 01/06/2017)
LCA of the new PVC-free blood bag (new deadline 01/03/2017)
Technical report (new deadline 01/01/2017)
After-LIFE Communication Plan (included in final report)
Final project report (new deadline 30/09/2017)